The transformer, the one in the electric grid – is it holding up AI?
The transformer, the one in the electric grid – is it holding up AI?
AI summary
Large power transformers, built on a 19th-century design, have become a key bottleneck in AI infrastructure: demand nearly tripled between 2019 and 2025, costs rose 80%, and orders can take over three years to fill. The shortage stems from limited grain-oriented electrical steel (only about ten mills worldwide can make it), tight copper supply, and the fact that each transformer is custom-built with no spares. Data-center grid demand is projected to reach about 134 gigawatts by 2030, and workarounds like on-site gas plants face their own turbine backlogs reaching about 116 gigawatts by mid-2026.